CASE STUDY:
AT&T WIRELESS
(COLUMBIA, MD)

Project:

PPL Telcom (Pennsylvania Power & Light – Telcom Division) hired MCG to design, engineer, construct and splice a 3-mile fiber optic cable in the city of Columbia in Howard County, Maryland, a tightly-planned, high-tech metropolis with a population of 97,000. The project completion deadline was eight months.

Challenge:

Strict county regulations prohibited MCG from stringing the cable from aerial poles, so an underground route was chosen. But the area required for the cable run was already congested with existing underground utilities, making design and construction difficult.



Implementation:

Using its arsenal of high-tech, GPS-driven mapping tools, MCG established a safe route for the underground cable, a process which took four weeks. It then requested permission from the county for a subsurface directional bore.

The county, however, insisted that additional stipulations between PPL Telecom and Howard County would have to be agreed to before construction could begin. MCG acted as liaison between PPL and county officials, a process which took three months to complete.

At the conclusion of these negotiations, and with less than four months before the contract deadline, MCG received another surprise from the County when it reported that MCG's initial design for the cable run conflicted with Columbia's existing underground infrastructure.

MCG quickly redesigned the cable route to satisfy the County's engineer in just one week, and construction of the cable began.


Result:

Even with all the unexpected delays, MGG completed the design, construction and splicing of the 3-mile underground cable within the eight-month deadline. The project was also completed at a cost 30 percent below what was called for in PPL’s contract.

Home       About us       Services       Solutions       Clients & Partners       Contact       Links
site by: eMediaNation     Copyright 2005 © Metropolitan Communications Group, Inc. All rights reserved.